Our Lady of Fatima

LOCATION:
Lafayette, LA

The Fatima School/Church parking lot was a 60,000 SF paving and drainage rehabilitation project. The main scope of the project consisted of the removal and reclamation of the existing asphalt surface as well as the removal and replacement of the existing subsurface drainage system.

Other aspects of the project:

    • Installation of site lighting
    • Installation of irrigation and landscaping
    • New parking canopy
    • Concrete paving and curbing

Mourain Construction was given only 65 days to complete the project and to the delight of their customer completed the project in 55 days giving the school 10 days to spare before school started again.